PLN 3 Million in Financing to Deliver a Public-Sector Contract

How a company secured capital for materials, suppliers and project launch despite being unable to increase its bank financing

A company delivering public-sector contracts needed capital to begin work on a large order and cover costs arising before the first payments from the contracting authority were received. The signed contract provided a predictable source of future revenue, but the company’s existing credit exposure limited its ability to obtain additional bank financing. PaveNow arranged PLN 3 million in financing, released in three tranches and aligned with the project delivery schedule. Part of the funding was transferred directly to suppliers, while subsequent disbursements were linked to progress under the contract.

Amount

PLN 3,000,000

Industry

Public-sector contract delivery

Purpose

Project launch, materials and payments to suppliers and subcontractors

Disbursement

Three tranches aligned with successive project stages

Repayment source

Revenue generated under the contract

Who was the client?

The client was a company specialising in the delivery of public-sector contracts. It had relevant industry experience and had secured another large order that required substantial capital expenditure before the first payments were received.

The company was not seeking funding to rescue an unprofitable business. It had a specific contract, a clearly defined scope of work and predictable future cash inflows. The challenge resulted from the timing gap between project expenditure and payments received for completed stages of the contract.

What was the purpose of the financing?

The purpose of the financing was to provide the funds required to begin delivering the contract and maintain continuity of work until the first payments were received.

In practice, the capital was needed for the purchase of materials, payments to suppliers, subcontractor fees and other operating expenses connected with successive stages of the project.

In projects of this kind, costs arise before revenue. The company must first order materials, commence work and engage contractors. Only afterwards does it receive payment for a completed project milestone.

What was the challenge?

The client had a signed contract and a predictable source of future revenue but could not increase its bank financing because of its existing credit exposure.

Without additional capital, the company risked delays in starting the work, difficulties paying suppliers and subcontractors on time and, ultimately, disruption to the delivery of a profitable contract.

The challenge was therefore not limited to securing a substantial amount of funding. The financing also had to be structured so that capital became available in line with the actual project schedule, while some payments could be made directly to entities involved in delivering the contract.

Financing mechanism

How was the financing aligned with the contract schedule?

The company had to cover project costs before receiving payment for completed stages. The financing was therefore released in line with the actual progress of the contract.

1

Upfront costs

Materials, suppliers and subcontractors had to be paid before the first contract revenue was received.

2

Staged disbursement

Capital was released in three tranches according to project progress and current funding requirements.

3

Contract revenue

Repayment was based on revenue generated through the delivery of the public-sector contract.

Key element: part of the financing could be transferred directly to suppliers and subcontractors involved in delivering the contract.

How did PaveNow structure the financing?

PaveNow arranged PLN 3 million in financing, divided into three tranches aligned with the contract delivery schedule.

The first tranche enabled the client to begin work and cover the initial project costs. The second was allocated to payments for suppliers and subcontractors, with part of the funding transferred directly to the relevant entities.

The third tranche was released after an agreed project milestone had been completed. Instead of receiving the full amount at once, the client accessed the capital at the stages when it was actually required.

This structure linked the disbursement of funds to project progress and reduced the cost of holding capital that had not yet been put to use.

Financing parameters

Amount

PLN 3,000,000

Disbursement

Three tranches

Purpose

Financing the delivery of a public-sector contract

Use of funds

Materials, suppliers, subcontractors and project delivery costs

Repayment source

Revenue generated under the contract

Challenge

Inability to increase bank financing despite a signed contract and predictable future cash inflows

What did the financing enable?

The financing allowed the client to begin delivering the contract according to schedule, order the required materials and settle payments with suppliers and subcontractors on time. By receiving the funds in successive tranches, the company maintained continuity of work and reduced the risk of delays caused by insufficient working capital.

The most important outcome was therefore not simply securing PLN 3 million. It was the ability to deliver a profitable contract that could otherwise have been delayed or suspended due to a shortage of capital.

Non-bank financing involved a higher cost than a standard bank loan, but it enabled the company to generate revenue and profit from a contract that the bank was unwilling to finance.

What can other contractors learn from this case?

This case demonstrates that having a signed contract does not automatically provide access to additional bank financing. A company may have confirmed future revenue while still lacking sufficient borrowing capacity to fund the delivery of a new order.

For large contracts, the amount of financing is not the only important factor. The way the capital is released also matters. Staged disbursement makes it possible to align funding with successive project milestones, control how the capital is used and limit financing costs.

For companies delivering public-sector contracts, infrastructure projects and larger B2B orders, the key lesson is clear: a profitable contract may require financing long before the first payment is received. A properly structured financing solution can bridge this period without bringing project delivery to a halt.

Business financing

Want to check what type of financing fits your company’s situation?

Talk to the PaveNow team and explore solutions for companies that need capital for day-to-day operations, larger projects, invoices, public-law obligations or growth.

Mateusz

Financing advisor

+48 889 274 772

Jakub

Financing advisor

+48 889 277 016

or email us at: finansowanie@pavenow.io
Availability: Monday–Friday, 9:00–17:00.